Most finishing problems we see on projects are not caused by poor materials but by the wrong sequence of work: tiles broken to run a forgotten cable, or paint redone after the air conditioning is installed. Knowing the finishing stages in the right order saves time and money and protects the quality of the result.
In this guide we set out the finishing stages for apartments and villas as we carry them out on our projects in Riyadh and the Eastern Province, from receiving the shell building to final handover.
Before any work on site, lock in the architectural, electrical and plumbing drawings, choose the main materials and ask for a clear bill of quantities. This stage determines most of the budget, and every change after it costs more.
Electrical conduits, lighting points and sockets, water and drainage lines, and AC routes are installed before any plastering. Pressure-test the water pipes and photograph the routes; they are your reference for any future maintenance.
Next comes waterproofing for roofs and bathrooms, followed by plastering that prepares the walls for final finishes. In the Eastern Province climate especially, good insulation prevents major maintenance costs later.
Once the plaster has dried, suspended and gypsum ceilings are installed, then flooring in porcelain, marble or parquet, then painting in stages: filler, primer and final coats. Leave the last coat of paint until after doors and lighting are fitted so it hides any installation marks.
This covers fitting doors, kitchens, sanitary ware, lighting and AC units, followed by cleaning and a final inspection. Ask for a handover walk-through with a written snag list, do not sign the final handover until it is closed, and keep the warranties for materials and workmanship.